Match List I (Activity) with List II (Technique) and select the correct answer using the code given below the Lists:
List I
A. Line Balancing
B. Product Development
C. Forecasting
D. Quality ControlList II
1. Value analysis
2. Exponential smoothing
3. Control chart
4. Selective control
5. Rank position matrix
b. A→5, B→3, C→2, D→1
c. A→2, B→3, C→4, D→1
d. A→5, B→1, C→2, D→3
asked in Mechanical Paper-2, 2005
View Comments [0 Reply]
-
15.
-
16.
Match List I (Production Control Function) with List II (Explanation) and select the correct answer using the code given below the Lists:
List I
A. Bill of Materials (BOM)
B. Capacity Resource Planning (CRP)
C. Material Requirement Planning (MRP)
D. Master Production Schedule (MPS)List II
1. A technique for determining the
quantity and timing of dependent
demand items
2. A technique for determining personnel
and equipment capacities needed to
meet the production objective
3. Specifies what end items are to be
produced and when
4. The part numbers & quantity required
per assembly
b. A→3, B→2, C→1, D→4
c. A→4, B→2, C→1, D→3
d. A→3, B→1, C→2, D→4
asked in Mechanical Paper-2, 2005
View Comments [0 Reply]
-